New PPL Projects

In the next couple of months, PP&L contractors will begin work on three different projects throughout the Township.  They are:

  1. Two new 69kV lines, which run parallel out of the future Williams Grove substation and head north towards Diehl Road area.
  2. A rebuild of the existing 230kV line, which runs near the Williams Grove substation.
  3. A maintenance project to the same 230kV line, beginning from the Williams Grove substation on the west side and running northwest through Monroe Township and up to Silver Spring Township.

PP&L has provided a FAQ sheet and map for review.  230kVRebuild FAQ Sheet and Map.

For more information or questions about the projects, contact the landowner rep Judy Buckner at 412-780-6268 or by email at jbuckner@contractlandstaff.com.

SHARE